Tasmania's Macquarie Point stadium precinct will cost $1.54 billion, up from $1.13 billion, breaking the state's pledged $875 million funding cap. Treasurer Eric Abetz says state borrowings will cover the shortfall while the government pursues more from federal and AFL partners.
KEY TAKEAWAYS
Cap broken, borrowings to fill the gap
Tasmania's Macquarie Point stadium precinct will cost $1.54 billion, the state government confirmed on 24 November 2026, after the stadium-delivery estimate rose from $1.13 billion to $1.23 billion and blew past the state's self-imposed $875 million funding cap.[1] Treasurer Eric Abetz said any shortfall beyond that cap would be funded through state borrowings while the government pursued additional contributions from project partners.[1]
The disclosed figures break down as $1.23 billion for stadium delivery, $132 million for precinct infrastructure including a centralised car park and power upgrades, and $183 million for project delivery, totalling $1.545 billion.[1] The government said the final procurement phase remains under way and the final cost may still change.
What the state had promised
To win the votes it needed in the Legislative Council, the government had committed to limit the state's contribution to $875 million, the ABC reported.[2] Premier Jeremy Rockliff confirmed the revised cost will not return to parliament for approval.
Who else is paying
The Commonwealth's Federation Funding Agreement estimates a $240 million contribution to the Macquarie Point precinct, covering construction of a multipurpose stadium.[3] Tasmanian Treasury records identify a further $15 million AFL contribution to the project.[4]
The AFL has stipulated that a roofed Macquarie Point stadium with capacity of at least 23,000 seats is a condition of granting Tasmania its 19th licence.[5] Those combined contributions from Canberra and the AFL total $255 million, leaving state borrowings to absorb the remainder beyond the $875 million cap.
Reasons given for the blowout
The government attributed the revised estimate to the war in Iran, sustained high oil and materials prices, higher labour costs, project complexity and complexities associated with the parliamentary-approved order.[1] Premier Jeremy Rockliff said every generation gets a handful of opportunities to shape the future, and described the stadium as one of those opportunities, while Treasurer Eric Abetz said the multipurpose stadium would draw visitors to Tasmania, support year-round events and strengthen the economy for decades.[1]
SOURCES & CITATIONS
- Macquarie Point Project Cost Update, Premier of Tasmania
- ABC News: Hobart's stadium and precinct costs rise to $1.54b
- Macquarie Point Federation Funding Agreement Infrastructure, Tasmanian Parliament
- RTI records on Macquarie Point funding contributions, Tasmanian Treasury
- Tasmania to enter VFL and VFLW in 2026, AFL