TLDR
A $32 billion data-centre campus near Dalby cleared its federal environmental referral in about two months. The Queensland Productivity Commission says approvals averaged more than 1,150 days. Extending that speed to all applicants is the fix, not penalising the data centre for moving quickly.
A federal gate cleared in two months, and what that exposes
The federal environmental referral for Western Downs Digital Park was lodged on 28 September 2026. A decision was published by late November, about two months later, under EPBC 2026/10667.[1] The project is a four-building data-centre campus near Dalby, with roughly 1.44 gigawatts of information-technology capacity and a maximum permanent disturbance footprint of about 178.7 hectares.[1]
That speed deserves attention. A referral decision is one gate of many, and Zerra says the development remains subject to local and state assessment and approval processes that are still outstanding.[3] Speed and rigour are not mutually exclusive, and the two-month turnaround does prove that government can examine a major proposal and give proponents a clear answer without converting the process into an endurance contest.
That proof is uncomfortable for everyone who has watched smaller applications disappear into multi-year queues.
What the Queensland Productivity Commission found about delay
The Queensland Productivity Commission's interim report makes the contrast stark. Queensland EPBC approval decisions took around 700 days on average in 2000 to 2009 and more than 1,150 days in 2018 to 2025, with infrastructure and residential projects recording the longest waits.[2] Those are not abstract categories. They cover the homes, roads and premises on which regional businesses and families depend.
The Commission estimates that delays tied to federal environmental obligations cost Queensland proponents $4.9 billion to $7.7 billion a year before the 2025 reforms.[2] Stakeholders told the Commission that information requests stopping the clock are a key contributor to delay, and that a pragmatic, capable regulator can materially improve timeliness.[2]
| Measure | Figure |
|---|---|
| Western Downs Digital Park federal referral | Started 28 September 2026, decision published about two months later |
| Average federal approval in Queensland before the 2025 reforms | More than 1,150 days |
| Estimated yearly cost of delay to Queensland proponents | $4.9 billion to $7.7 billion |
Clear rules, proportionate information requests and decisions made on time are what the system owes every applicant, another round of conditions or a new regulator to supervise the regulator adds nothing.
Siding with Prenzler on the right fix
Angela Prenzler of Western Downs Says Pause has put the fairness problem plainly. "It's actually longer to get a shed approved on your property than what it is for a data centre to be approved in our council region, it seems to be," she said.[5] The comparison lands because the asymmetry is galling and well-documented.
Where the argument goes next matters. Making the data centre slower does nothing for the farmer waiting on a shed approval. The remedy is giving the smaller applicant the same predictable, timely treatment, not pulling the larger one back into the queue.
The Climate Council estimates that, if Western Downs Digital Park is not matched with new renewables and storage, it could produce emissions equivalent to about 3.1 million cars a year by 2035.[4]
Zerra chief executive Dave Cooper said the company recognises that "infrastructure of this scale must be delivered responsibly, particularly in relation to energy and water."[3] Zerra also says it will fund the dedicated Braemar substation connection and project-specific network infrastructure rather than passing those costs to other electricity users.[3]
Queensland can welcome investment, examine its consequences and still refuse to accept needless delay as a fixed feature of the system. Council and state approvals for Western Downs Digital Park remain outstanding, and the scrutiny those processes provide is exactly what the remaining gates exist to deliver.
KEY TAKEAWAYS
SOURCES & CITATIONS
- EPBC referral summary, Western Downs Digital Park (EPBC 2026/10667)
- Queensland Productivity Commission, EPBC Summary Interim Report, November 2026
- Western Downs Digital Park, Zerra DC official site
- Climate Council, Pollution Pipeline: Australia's Dirtiest Data Centres
- ABC News, Western Downs Digital Park federal environmental approval