TLDR
NEXTDC slashed its FY27 net revenue guidance by roughly A$140 million after grid distributor Jemena suspended 66kV line works for its M3 Melbourne data centre, citing community opposition and absent council consent. The next power increase for M3 is now expected in FY28, and NEXTDC has frozen all new development projects pending a board capital review.
KEY TAKEAWAYS
Jemena's suspension triggers guidance overhaul
NEXTDC revised its FY27 net revenue guidance to A$475 million to A$500 million, down from A$615 million to A$640 million, after grid distributor Jemena Electricity Networks suspended the 66kV line augmentation works needed to deliver more power to M3 Melbourne.[1] The ASX disclosure, dated 21 October 2026, also lowered FY27 underlying EBITDA guidance to A$245 million to A$265 million, down from A$385 million to A$410 million.[1]
Chief executive Craig Scroggie said: "Jemena has suspended parts of the network works required for the next increase in grid supply to M3 Melbourne. Jemena has attributed the suspension to community and stakeholder opposition to the works and to the absence of local council consent pending further consultation. On Jemena's current indicative estimate, we expect that increase during FY28."[1]
What Jemena suspended and when
Jemena suspended parts of its 66kV line augmentation works for M3 Melbourne in September 2026, citing safety concerns and lack of site access, and does not expect to recommence them before February 2027.[1][2]
M3 Melbourne, located in West Footscray, is a 225 MW Tier IV certified data centre designed as a digital gateway for Victoria.[4] A planning application for M3 Stages 6 and 7 (PA2604231) was lodged in February 2026 under the Victorian Government's Development Facilitation Program, with a decision expected only after the 28 November 2026 state election, likely in 2027.[3]
A$140m stripped from guidance
Scroggie confirmed the precise figure removed from the company's forward estimates. "We have taken the affected M3 contracts out of FY27 guidance until we can reliably estimate their contribution. The August guidance included approximately A$140 million of each of net revenue and Underlying EBITDA from those contracts. The timing and scale of their contribution remain uncertain."[1]
Capital expenditure guidance also moved lower, to A$4,500 million to A$5,000 million for FY27, down from A$5,250 million to A$5,750 million, including about A$230 million of capitalised interest.[1]
Project freeze and potential site sales
NEXTDC has paused all new development projects and land acquisitions, and its board will evaluate capital recycling opportunities including potential sales of selected development sites.[1] Shares fell roughly 40 per cent when trading resumed after the announcement.
Scroggie said the company's balance sheet remained intact. "We have approximately A$8.7 billion of liquidity at 30 September 2026 and we are in compliance with our covenants."[1] That liquidity comprised A$1.275 billion of cash and A$7.4 billion of undrawn senior debt facilities as at 30 September 2026.[1]
SOURCES & CITATIONS
FREQUENTLY ASKED QUESTIONS




